J.J. Carroll Construction Updates

As we embark on the J.J. Carroll Redevelopment, we are committed to keeping our neighbors informed while we are under construction.

Return to the J.J. Carroll main page

We will use this website to upload regular updates on the construction schedule. See below for links to documents of the current and past construction updates.  

UPCOMING EVENTS 

The Boston Fire Department will be holding training sessions in and around the J.J. Carroll buildings from June 21 through June 30.   

 

If you have immediate concerns about safety, noise or access, please contact the appropriate designated representative. Contact information is below.

Contact Information

If there are questions or concerns that relate to immediate/emergency site conditions, please email:

Dana Marcotte
Project Superintendent
Dmarcotte@dellbrookjks.com

Lou Mascolo
Project Manager
LMascolo@dellbrookjks.com 

If there are questions or concerns that relate to schedule or upcoming work, please call or email:

Lisa Kozol
Project Manager
(617) 912-8464
lkozol@2lifecommunities.org

Joseph O’Toole
Director of Facilities
(617) 912-8426
jotoole@2lifecommunities.org

Denise Hamilton
Executive Director, Brighton Campus
(617) 912-8426
dhamilton@2lifecommunities.org

 

Overall Schedule

Est. Start Est. Completion

Demolish Existing Building

July 2021 September 2021

Building Construction

Sept 2021 April 2023

Affirmative Marketing & Leasing

Sept 2022 March 2023

Site Work/Landscaping

Jan 2023 April 2023

Construction Completion

March 2023 April 2023

Residential Occupancy

May 2023 Oct 2023

 